Auditor Tell NASA to Get Real – Maybe Humans on the Moon 2027 Not 2024

NASA Office of Inspector General – Office of Audits IG-22-003 (A-20-008-01) says NASA Artemis program will not land humans on the moon before 2027. The NASA Artemis program had been targeting to return humans to the Moon by late 2024 rather than 2028 as initially planned. NASA implemented modifications to its routine procurement and program…
Auditor Tell NASA to Get Real – Maybe Humans on the Moon 2027 Not 2024


NASA Office of Inspector General – Office of Audits IG-22-003 (A-20-008-01) says NASA Artemis program will not land humans on the moon before 2027. The NASA Artemis program had been targeting to return humans to the Moon by late 2024 rather than 2028 as initially planned. NASA implemented modifications to its routine procurement and program management practices in an attempt to accelerate the mission schedule and reduce costs.

The auditors indicate that SpaceX could have the Human Landing System ready by 2025.

Recent space flight programs have on average taken about 2 years between test and operational flights, SpaceX plans to launch its crewed HLS 1.2 years after its uncrewed demonstration mission. To their credit, the company’s rapid “design-build-fly” testing approach and in-house production facilities are unique capabilities that may allow for faster development and production timelines than previous NASA space flight programs.

SLS and Orion have also experienced technical challenges in later development phases as well as the effects of COVID-19 restrictions and severe weather events. Additionally, the Gateway and HLS Programs received significantly less funding in fiscal year (FY) 2021 than required to meet NASA’s initial acquisition strategy.

Artemis I mission elements now being integrated and tested at Kennedy Space Center, auditors estimate NASA will be ready to launch by summer 2022 rather than November 2021 as planned.

Although Artemis II is scheduled to launch in late 2023, auditors project that it will be delayed until at least mid-2024 due to the mission’s reuse of Orion components from Artemis I.

While the Advanced Exploration Systems (AES) Division—which includes HLS, Gateway, and next-generation spacesuits—is working on an integrated master schedule (IMS) for Artemis III that incorporates Exploration Systems Development (ESD) Division programs—SLS, Orion, and Exploration Ground Systems—the draft version does not include information on programs critical to Artemis that are outside of AES and ESD. Given the time needed to develop and fully test the HLS and new spacesuits, they project NASA will exceed its current timetable for landing humans on the Moon in late 2024 by several years.

$4.1 billion per Launch of SLS

NASA lacks a comprehensive and accurate cost estimate that accounts for all Artemis program costs. For FYs 2021 through 2025, the Agency uses a rough estimate for the first three missions that excludes $25 billion for key activities related to planned missions beyond Artemis III. When aggregating all relevant costs across mission directorates, NASA is projected to spend $93 billion on the Artemis effort up to FY 2025. Auditors also project the current production and operations cost of a single SLS/Orion system at $4.1 billion per launch for Artemis I through IV, although the Agency’s ongoing initiatives aimed at increasing affordability seek to reduce that cost. Multiple factors contribute to the high cost of ESD programs, including the use of sole-source, cost-plus contracts; the inability to definitize key contract terms in a timely manner; and the fact that except for the Orion capsule, its subsystems, and the supporting launch facilities, all components are expendable and “single use” unlike emerging commercial space flight systems. Without capturing, accurately reporting, and reducing the cost of future SLS/Orion missions, the Agency will face significant challenges to sustaining its Artemis program in its current configuration.

Subscribe on Google News

Read More

Total
0
Shares
Leave a Reply

Your email address will not be published.

Related Posts
Nuclear Fusion Power and Science
Read More

Nuclear Fusion Power and Science

I have a farely comprehensive understanding of the huge challenges needed to create commercial nuclear fusion power. This is why I am more optimistic about molten salt nuclear fission. I try to explain this in two videos. However, this is a complex topic. I will try to state this as clearly and briefly as possible…
First SLS Launch Slips to August 2022 or Later
Read More

First SLS Launch Slips to August 2022 or Later

The Space Launch System failed another test sothe earliest possible launch is August. The next wet rehearsal test is hoped to be early June. At a May 5 briefing, NASA officials said they had made progress on two problems with the SLS and its mobile launch platform discovered during three attempted wet dress rehearsal (WDR)…
Tesla Manufacturing and Innovation Advantage
Read More

Tesla Manufacturing and Innovation Advantage

Tesla has vastly superior engineering talent and business and engineering processes. Tesla has the lead with drivetrain, battery and control systems and aerodynamics and materials. Tesla has about 70% of the US EV market and 20% of the global EV market. This market share is even more dominant when only EVs in the same price…
SpaceX Funded for On-Earth Rocket Cargo
Read More

SpaceX Funded for On-Earth Rocket Cargo

SpaceX a $102 million five-year US Air Force contract to demonstrate delivering cargo anywhere on earth (point to point) in an hour. The under one hour delivery is not specified in the contract but using the the SpaceX Starship would enable delivery of up to 220 tons in under one hour. There was a previous…